Construction Updates!

March 21, 2022 / Comments (0)

Uncategorized

Please note that following dates for construction and maintenance around the BCA Clubhouse. Dates are subject change and weather dependent.

Create Drainage Swale above Driveway – 3/23 – 4/2: Some closures during the work day, Evenings accessible

Clearing & Grubbing, Install Bio Swale – 4/2 – 4/9: No restrictions. But Proceed With Caution during the day

Rain Garden, 12×12 Catch Basin, Overflow – 4/10 – 4/14: No restrictions. But Proceed With Caution during the day

Install Yard Drain, Ductile Iron Pipe under Driveway, and Catch Basin – 4/16 – 4/18: Probable Closure, Driveway impassable during the day.

Landscape Restoration 4/19-4/21: No restrictions. But Proceed With Caution during the day

Driveway and Parking Lot Paving – 5/2 – 5/6:  Closure, Driveway and parking lot impassable.